Projects in Construction

Collapse All Expand All
Expand List item 18589Collapse List item 18589  Reach A

Reach A: Reach A consists of the Sacramento River East Levee between Gateway Oaks Drive to Farm Road. The length of this reach is approximately 3.5 miles. The upstream 2.3 Miles of the project will widen the existing levee a minimum of 15 feet to allow construction of an underground cutoff wall with a maximum depth of approximately 142 feet.  This widening will also flatten the landside levee slope. Beneath Interstate 80, a seepage berm will be constructed on the land side of the levee. The remaining 1.2 miles consists of levee widening that includes a drained seepage berm. The pumping stations at City Sump 160 and the two Pumping Plants at the RD1000 office will also be improved with this project.  The Post-Authorization Change Report and Interim Reevaluation Report American River Watershed evaluated the use of a seepage berm in certain areas of this reach. The contract was awarded on Sep. 23, 2021 and construction began in Aug. 2022. For more information on Reach A, please visit the Reach A webpage.

Expand List item 18590Collapse List item 18590  Reach B

Sacramento River east levee from Farm Road upstream (north) to Elverta Road. The length of this reach is approximately 9.7 miles. The general improvements include widening the existing levee by construction of an adjacent levee, installation of approximately 4.3 miles of a seepage cutoff wall that ranges in depth between approximately 40 and 115 feet, and installation of approximately 5.6 miles of seepage berms that range in width from approximately 80 to 300 feet, and flattening the landside levee slope. A portion of the Reach B features were constructed by the Non-Federal Sponsors upstream of approximately Powerline Rd, apart from several “windows” within the alignment that were left for the USACE to construct. The USACE Reach B contract spans along Garden Hwy from just downstream of Powerline Road, south to Farm Road and consists of 2.3 miles of adjacent levee construction, an irrigation pipeline relocation, improvements to Pumping Plant #3, and seepage berm construction. The contract was awarded on Nov. 14, 2019.

 

Reach B I-5 Window: The contract was awarded on May 7, 2021. Construction work consisted of seepage berm extension and general earthwork underneath the I-5 overpass and the junction of North Bayou Way at the Elkhorn Boating Facility. Construction was substantially completed in 2023.

 

 

Reach B PP#5This is a Flood Damage Reduction project located just north of downtown Sacramento located in Reach B. Upgrading of interior drainage pumping plant and relocation of discharge pipes crossing levee. The design will be complete in 2026 and construction is scheduled to begin in 2027.

Reach B Riverside Pumping Plant Relocation: On behalf of the Non-Federal Sponsors, the Natomas Central Mutual Water Company (NCMWC) will be replacing the Riverside Pumping Plant and relocating the discharge pipes up and over the levee and above the 200-year flood elevation. This will occur in two phases with the first being the pumping plant replacement which was awarded in Summer 2022 with construction 100% complete. The second phase is the relocation of the discharge pipes which is scheduled to begin late 2027.

Reach B Elkhorn Pumping Plant Relocation: On behalf of the NFS, the NCMWC will be replacing the Elkhorn Pumping Plant and relocating the discharge pipes up and over the levee and above the 200-year flood elevation. This will occur in two phases with the first being the pumping plant replacement which was awarded in April 2024. Construction began in summer 2024 and lasted two seasons. The second phase is the relocation of the discharge pipes, which is scheduled to begin late 2027.

Expand List item 18591Collapse List item 18591  Reach C

Sacramento River east levee from Elverta Road upstream (north) to Sankey Road at the west end of the south levee of the Natomas Cross Canal. The length of this reach is approximately 5 miles. The general improvements include widening the existing levee by construction of an adjacent levee, installation of approximately 4.6 miles of seepage cutoff wall that ranges in depth between approximately 19 and 65 feet, and installation of approximately 2.7 miles of seepage berms that range in width from between approximately 100 to 500 feet, and flattening the landside levee slope.

Reach C Pritchard Lake Pumping Plant Relocation: On behalf of the Non Federal Sponsors, the Natomas Central Mutual Water Company replaced the Pritchard Lake Pumping Plant in 2015, except for the installation of one of the three new pumps. The installation of the last pump and the relocation of the discharge pipes up and over the levee and above the 200-year flood elevation will occur during the second phase of construction and is scheduled for Fall 2027. 

Expand List item 18592Collapse List item 18592  Reach D

Natomas Cross Canal south levee from Sankey Road upstream (northeast) to Howsley Road at the PGCC. The length of this reach is approximately 5.5 miles. The general improvements include widening the existing levee by fix in-place construction, and installation of a seepage cutoff wall that ranges in depth between approximately 60 and 75 feet, and flattening the landside levee slope. The construction contract was awarded on May 10, 2018. Construction began Aug. 13, 2018, with physical construction completion on Nov. 22, 2021.

 

Reach D, Pumping Plant #4: Flood Damage Reduction project in the northwest corner of Natomas Basin adjacent to the Natomas Cross Canal. Work involves demolition and rebuild of the pumping plant including elevation of three stormwater pipes 10 feet to design water surface elevation, and a new electrical station and pumping plant. Work includes the demolition and replacement of Pumping Plant 4 including elevation of three stormwater pipes 10 feet to design water surface elevation, and a new electrical station and pumping plant. The construction contract was awarded on Feb. 11, 2021, and construction began on May 18, 2021, with physical construction completion anticipated for Fall of 2027.

 

Reach D, HWY99:  Reach D levee improvements were completed by the Non Federal Sponsors in 2010 with the exception of an approximately 690-foot section (window) of the levee where the Highway 99 bridge crosses over the top of levee. The Hwy 99 project includes a 750-foot-long cutoff wall which overlaps and closes the gap between the cutoff walls constructed by the NFS. The construction contract was awarded January 17, 2024, and construction began in June 2024, with physical construction completed in the Fall of 2025.

Expand List item 18593Collapse List item 18593  Reach E

Pleasant Grove Creek Canal west levee from Howsley Road upstream (south) to Sankey Road. The length of this reach is approximately 3.4 miles. The general improvements include widening the existing levee by fix in-place construction, installing an adjacent levee, installation of a seepage cutoff wall that ranges in depth between approximately 38 and 50 feet, flattening the landside levee slope and replacement of (5) underdrain culverts and gatewells. The contract was awarded on April 10, 2023, and construction began June 2023. The construction contract was awarded on April 10, 2023 and construction began in June of 2023, with physical construction completion anticipated for Fall of 2026.

Expand List item 18594Collapse List item 18594  Reach F

The Natomas East Main Drainage Canal west levee from Sankey Road downstream (south) to Elverta Road.  The length of this reach is approximately 4.7 miles. The general improvements include widening the existing levee by fix in-place construction, levee widening, flattening the landside levee slope and installation of a patrol road. The design is 100% complete and construction is planned for the 2028/2030 construction seasons.

Expand List item 18595Collapse List item 18595  Reach G

The Natomas East Main Drainage Canal west levee from Elverta Road downstream (south) to the drainage pumping station just upstream of Dry Creek.  The length of the reach is approximately 3.6 miles. The general improvements include improving the levee by fix in-place construction, and installation of a seepage cutoff wall with a depth of approximately 40 feet near Pump Station No. 6, levee widening, flattening the landside levee slope and installation of a patrol road. The design is 100% complete and construction is planned for the 2028/2030 construction seasons.

Expand List item 18588Collapse List item 18588  Reach H

The Natomas East Main Drainage Canal west levee requires cutoff wall improvements from the pumping station just upstream of Dry Creek downstream (south) to Arden-Garden Connector Bridge. The length of this reach is approximately 4.0 miles. The general improvements include improving the existing levee by fix in-place construction, and installation of a seepage cutoff wall with a depth of approximately 30-70 feet and flattening the landside levee slope. There are two pumping stations which will require the discharge pipes to be raised and installation of a landside maintenance road.  The design was done by AE firm Wood Rodgers. The construction contract was awarded on Jan. 23, 2019, and construction began May 2019, with physical construction completed May 2024.

Expand List item 18596Collapse List item 18596  Reach I

The Reach I project was planned to be constructed during two contracts of work.

Contract 1 - The Natomas Basin Reach I Contract is located on the reach of Natomas levee adjacent to the American River in Sacramento, CA. Reach I Contract 1 includes installation of approximately two miles of cement-bentonite cutoff walls between Gateway Oaks Boulevard and Northgate Boulevard, mostly centered on Garden Highway. The cutoff walls will have an average depth of 45 feet. Excavation spoils will be hauled to a site identified herein to be spread and compacted. A landside drainage blanket will be installed on the levee slope underneath Interstate 5. Relocation and/or removal of waterlines, sanitary force mains, and other utilities are included in the contract.  Multiple lane closures, road closures, and bicycle trail closures are also included. The construction contract was awarded on July 30, 2018, and construction began Oct 2018, with physical construction completed on Nov. 4, 2020. 

 

Contract 2 - The American River north levee from Northgate Boulevard downstream (west) to Interstate Highway 5. The length of this reach is approximately 1.8 miles. The general improvements include improving the levee by fix in-place construction, and installation of a seepage cutoff wall with a depth of approximately 37 feet, flattening the landside levee slope and installation of a patrol road. The Reach I project was planned to be constructed during two phases of work (contracts). Reach I Contract 1 included installation of the cutoff wall and was completed by USACE in Nov. 4, 2020. Reach I Contract 2 is in the final design phase and includes the landside improvements. Construction for Reach I Contract 2 is planned for the 2027 construction season.

Expand List item 31698Collapse List item 31698  Mitigation

Overall Natomas Mitigation includes creation of Woodland Mitigation in various sites including Novak and the Woodland Corridor, 80 acres of Giant Garter Snake Habitat and improvements to the West Drain to enhance connectivity between Giant Garter Snake habitats. The Natomas Basin is a unique ecological system separated from other systems by a circular levee system. A Biological Assessment was performed which accurately described the mitigation measures. As a result of this coordination the BO’s received for the previous four phases have obtained mitigation measures similar to what was proposed in the BA. Project mitigation needs have been coordinated with U.S. Fish and Wildlife Service, National Marine Fisheries Service, and the California Department of Fish and Game.

Natomas Levees Overview

Contact Information

For more information on Natomas Basin levee improvements, 
please contact us at the following:

Phone: 
916-557-5100

Email:
spk-pao@usace.army.mil

Mailing Address:
U.S. Army Corps of Engineers,  Sacramento District
Natomas Basin project
1325 J Street, Room 1640
Sacramento, CA 95814

Button to submit construction work inquiry or concern submission form

Natomas Basin Project Map

Natomas Basin

Sacramento's Natomas Basin is one of the most at-risk areas in the nation for catastrophic flooding. Improvements to Natomas levees were originally authorized as part of the Corps' American River Common Features project in 1996, intended to improve the system of levees throughout the greater Sacramento area. Since then, the scope and cost of Natomas levee improvements have increased after high water events in 1997 and 2006 showed serious underseepage in the basin. In 2010, a post-authorization change report was completed detailing the Corps' recommended plan for improving Natomas levees. The project to improve the 42-mile ring of levees surrounding the basin was authorized in 2014. The Sacramento Area Flood Control Agency completed the first 18 miles of levee improvements, and USACE had led construction on the remaining 24 miles.  

Recent Documents

Reach B, Cache Creek Borrow Site, Draft Supplemental EA - December 2020
This document had a 30-day public review and comment period that closed on January 28, 2021. 
Draft SEA Report
Supplemental Plates
Appendix A - CEQA Document
Appendix B - Construction Emissions Estimates
Appendix C - Correspondence Regarding Special Status Species
Draft FONSI

 

Reach D, Pumping Plant 4, Draft Supplemental EA - September 2020
This document had a 30-day public review and comment period that closed on November 4, 2020. 
Notice of Availability
Draft Report
Supplemental Plates
Draft FONSI

 

Reach B, Interstate 5 Window Draft Supplemental EA - July 2020
Draft Report
Draft FONSI

Latest Project News

CONSTRUCTION UPDATE

  • The Vault at Pumping Plant 1B, located at 1633 Garden Highway, is complete. Traffic has been reopened in both directions near RD 1000 (1633 Garden Hwy) however traffic remains open one-way to eastbound Garden Highway traffic from west of RD1000.
  • Construction activities are currently on hold until April 14, 2026. Utility relocation work is ongoing.
  • Access to local residences and businesses will remain open at all times.
  • We appreciate your patience and understanding as we work to enhance flood protection for the Natomas Basin.
    We will continue to update this page with current information regarding the project and upcoming closures as we obtain details.

Project News Archives

Construction Update for October 2025 

Construction Update for July 2025

Construction Update for April 2025

Construction Update for January 2025

Construction Update for October 2024

Construction Update for July 2024

Construction Update for April 2024

Construction Update for January 2024

Construction Update for October 2023

Construction Update for July 2023

Construction Update for April 2023

Construction Update for January 2023

Construction Update for September 2022

Construction Update for August 2022

Construction Update for July 2022

Construction Update for April 2022

Construction Update for January 2022

Natomas Reach A site preparation activities set to continue (October 2021)

Construction Update for March 11, 2021

Construction Update for January 11, 2021

Reach A site preparation activities set to begin this November (Oct 2020)

Construction Update for June 18, 2020

Construction Update for May 21, 2020

Garden Highway Closure Information

Corps to resume Natomas levee work, close Garden Highway on April 23

Construction Update for April 20, 2020

Natomas levee improvements hit high gear (April 2020) 

Construction Update for March 18, 2020

Construction Update for March 6, 2020

Construction Update for January 24, 2020

Construction Update for December 13, 2019

Construction Update for October 9, 2019

Rep. Doris Matsui tours Garden Highway progress (Sep 2019)

Levee improvement work begins in lower Natomas Basin (Jun 2019)

Construction Update for June 14, 2019

Construction Update for June 6, 2019

Construction Update for May 13, 2019

President's FY19 budget allocates more than $200 million for Sacramento District projects (Feb 2018)

Proposed north Natomas flood risk reduction project out for public review (Aug 2017)

Corps awards $19.5 million contract for Natomas levee construction (July 2017)

$20.46 million contract award set to kick off Natomas Basin levee improvements (Feb 2017)

Natomas Basin project agreement signals transition to levee improvement construction (Aug 2016)