Sacramento River east levee from Farm Road upstream (north) to Elverta Road. The length of this reach is approximately 9.7 miles. The general improvements include widening the existing levee by construction of an adjacent levee, installation of approximately 4.3 miles of a seepage cutoff wall that ranges in depth between approximately 40 and 115 feet, and installation of approximately 5.6 miles of seepage berms that range in width from approximately 80 to 300 feet, and flattening the landside levee slope. A portion of the Reach B features were constructed by the Non-Federal Sponsors upstream of approximately Powerline Rd, apart from several “windows” within the alignment that were left for the USACE to construct. The USACE Reach B contract spans along Garden Hwy from just downstream of Powerline Road, south to Farm Road and consists of 2.3 miles of adjacent levee construction, an irrigation pipeline relocation, improvements to Pumping Plant #3, and seepage berm construction. The contract was awarded on Nov. 14, 2019.

Reach B I-5 Window: The contract was awarded on May 7, 2021. Construction work consisted of seepage berm extension and general earthwork underneath the I-5 overpass and the junction of North Bayou Way at the Elkhorn Boating Facility. Construction was substantially completed in 2023.
Reach B PP#5: This is a Flood Damage Reduction project located just north of downtown Sacramento located in Reach B. Upgrading of interior drainage pumping plant and relocation of discharge pipes crossing levee. The design will be complete in 2026 and construction is scheduled to begin in 2027.
Reach B Riverside Pumping Plant Relocation: On behalf of the Non-Federal Sponsors, the Natomas Central Mutual Water Company (NCMWC) will be replacing the Riverside Pumping Plant and relocating the discharge pipes up and over the levee and above the 200-year flood elevation. This will occur in two phases with the first being the pumping plant replacement which was awarded in Summer 2022 with construction 100% complete. The second phase is the relocation of the discharge pipes which is scheduled to begin late 2027.
Reach B Elkhorn Pumping Plant Relocation: On behalf of the NFS, the NCMWC will be replacing the Elkhorn Pumping Plant and relocating the discharge pipes up and over the levee and above the 200-year flood elevation. This will occur in two phases with the first being the pumping plant replacement which was awarded in April 2024. Construction began in summer 2024 and lasted two seasons. The second phase is the relocation of the discharge pipes, which is scheduled to begin late 2027.