Banner - Sacramento Weir

Link to Sacramento Levee Upgrades Project Overview

Link to Sacramento Levee Upgrades - American River Levee Work

Link to Sacramento Levee Upgrades - Sacramento River Levee Work

Current Page - Sacramento Levee Upgrades - Sacramento Weir

Link to Sacramento Levee Upgrades - Mitigation

Button to subscribe for construction and traffic email updates


Sacramento Weir History and Future


Sacramento Levee Upgrades Overview

Documents

Sacramento Weir Widening Record of Decision (ROD) - September 2021
Signed Record of Decision

Sacramento Weir Widening Final Supplemental EIS/EIR - August 2021 (UPDATED)
Final SEIS/SEIR Report
Final SEIS/SEIR Appendices

Sacramento Weir Widening Draft SEIS/SEIR - July 2020
Notice of Availability
Draft SEIS/SEIR Report
Draft SEIS/SEIR Appendices

Related Topics

Looking for more information about the neighboring Lower Elkhorn Basin Levee Study (LEBLS) Project
Project web page
Contact: LowerElkhorn@water.ca.gov

Contact Information

For more information on
Sacramento Levee Upgrades,
please contact us at the following:

Phone:
916-557-5100

E-mail:
spk-pao@usace.army.mil

Mailing Address:
U.S. Army Corps of Engineers,
Sacramento District
1325 J Street, Room 1513
Sacramento, CA 95814

First major upgrade in Sacramento Weir's 109-year history

The U.S. Army Corps of Engineers is funding expansion of the Sacramento Weir. The project involves widening the 1,950-foot weir an additional 1,455 feet to the north.

The weir's 48 manually-operated gates will remain intact. The expansion includes constructing a passive weir that widens the surface area to allow additional floodwaters from the Sacramento and American Rivers to flow over the weirs and into the bypasses.

The Sacramento Weir Widening Project is split into two projects: 

1.  The Sac Bypass Widening project is  in construction and managed by the California Department of Water Resources (DWR).  Please contact DWR at the below link if you have any questions with regards to the Lower Elkhorn Basin Levee Setback (LEBLS) Project. 

2.  Sacramento Weir Widening Project construction is underway led by the USACE, Sacramento District.  

USACE, Sacramento Area Flood Control Agency,  and the Central Valley Flood Protection Board supported by California Department of Water Resources partnered to construct this project, with an estimated completion date for flood features by 2027 and final site clean up and erosion control planting will be completed in 2028. 

Progress continues

Section - Current Project Activities
 

19 September 2025 - Update on Sacramento Weir Expansion Construction 

The U.S. Army Corps of Engineers identified vertical settlement that exceeded the design tolerances at the Sacramento Weir Expansion’s north abutment wall in early 2025 and is designing a solution to address it. The north abutment wall is one of the 26 supports for a future bridge along the overall Weir Expansion Construction project. None of the other constructed features are experiencing movement issues. Addressing the unexpected movement is expected to delay project completion by about one year, but the current Sacramento Weir remains fully operational and there are no impacts to public safety.  

Why Did This Happen?

Large, complex infrastructure projects often require adjustments due to real-world conditions that may not align with initial predictions. While we conduct subsurface investigations and analyses following industry standards and best geotechnical practices, unforeseen variations can still occur. To account for this, USACE includes cost and schedule contingencies. While we estimate a year delay, we’re confident this fix will stay within budget contingency.

At the north abutment, the underlying soil has responded in a manner that differs from the original design assumptions. We are performing additional subsurface investigations and installing instrumentation to better understand the slope soil movement so we can rebuild the abutment.

North Abutment Wall Timeline and Next Steps 

  • January - February 2025 – Routine monitoring of the north abutment. Movement remained within anticipated design tolerance. 
  • March 2025 – Movement exceeded tolerance limits, prompting evaluation. 
  • Spring–Fall 2025 – Engineers have been studying the issue and designing an appropriate solution. 
  • 2026 – Finalize cost estimate and construction schedule and begin corrective work. 
  • 2027 – Complete corrective work.

aerial image shows two weirs along a river with one on the left labeled as "Current Weir" and the one on the right labeled as "Weir Expansion Construction."

image shows a series of bridge piers lined up along a river with a blue circle on the far right of the image labeled as "North Abutment Wall."

image shows close up of a wall with a blue circle around it. This is showing the North Abutment Wall on the new Sacramento Weir Expansion.

­­­­­­­­­­­_________________________________________________________________________________

September 8, 2025- Update on Sacramento Weir Expansion Construction 

The Sacramento Weir Widening construction project is well underway after starting in July 2023. The project construction is continuing year-round but is weather dependent. Primary activities since July 2023 include:

  • Earthwork activities for the new North Levee setback, Old River Road embankment, and County Road 126 embankment.
  • Pile Driving Rigs will be onsite in 2026 to drive 20-inch diameter steel pipe piles at the North Abutment and will serve as the northern extent of the weir and bridge.
  • Dewatering system was installed which includes a network of white piping near the southern end of the project and is conveying water from groundwater pumps to allow for excavation activities below the groundwater level.
  • Vehicle Bridge expected to be completed by early 2027. Traffic control detour will remain in place until the vehicle bridge is completed along Old River Road.  
  • Fish Passage Structure concrete placements have been completed for the fish ladder and riprap placement is underway for the fish passage channel. Fish Passage Phase 2 project features were completed in 2024 including modifications to the Sacramento Weir stilling basin to address fish stranding, completion of a new rock-lined channel, and completion of a new earthen channel that connects to Tule Canal.

Section - Public Engagements


 

Sacramento Weir Widening Draft SEIS/SEIR Virtual Public Meeting
August 19, 2020  
Notice of Availability
Draft SEIS/SEIR Report
Draft SEIS/SEIR Appendices
Webinar Presentation Slides


Sacramento Weir Widening - Supplemental EIS/EIR Public Scoping 
Virtual meeting held April 13, 2020. Public comment period closed on May 1, 2020. See presentation slides below: 

Sacramento Weir Widening Public Meeting Presentation