American River Levees

Archive

News & Updates (Archive)

iconAmerican River Erosion Monthly Update (Oct 2024)

iconAmerican River Erosion Monthly Update (Sep 2024)

Bank Protection Working Group Meeting (Aug. 13, 2024)
his video from the Bank Protection Working Group covers such topics as the Lower American River Hydraulic Model Selection, Understanding Erosion Risk Drivers, Reliability of Vegetation as Erosion Protection, and Influence of Past Designs on Contract 3B. Use this Video Timestamps document to find specific topics and where in the video they are discussed, 

iconAmerican River Erosion Monthly Update (Aug 2024)

iconAmerican River Erosion Monthly Update (Jul 2024)

iconAmerican River Erosion Monthly Update (Jun 2024)

Special Event: Community Conversation regarding American River Common Features (April 8, 2024)
The Office of Congressman Ami Bera and team members from the U.S. Army Corps of Engineers Sacramento District held a virtual community conversation regarding the American River Common Features Project erosion control efforts.

iconAmerican River Erosion Monthly Update (Apr 2024)

Public Meeting: American River Common Features (ARCF) 2016 Draft SEIS-SEIR (Jan. 16, 2024)
This public meeting explained the AMERICAN RIVER COMMON FEATURES 2016 Flood Risk Management Project, Draft Supplemental Environmental Impact Statement / Subsequent Environmental Impact Report iconPresentation Slides iconVideo Link

Public Meeting: American River Common Features (ARCF) 2016 Draft SEIS-SEIR (Jan. 10, 2024)
This public meeting explained the AMERICAN RIVER COMMON FEATURES 2016 Flood Risk Management Project, Draft Supplemental Environmental Impact Statement / Subsequent Environmental Impact Report iconPresentation Slides iconVideo Link

Public Meeting: Lower American River Erosion Construction Update (H St to Howe Ave) (May 4, 2023)
In this meeting we discussed why the Lower American River Erosion project is needed, how we chose the design, environmental impacts, what to expect during construction, and future work we’ll be doing in the parkway. 
iconPresentation Slides iconVideo Link

American River Erosion Update for Contracts 1, 2, 3A (March 16, 2023)
This presentation was given to the River Park Neighborhood Association to inform them of the status on erosion control projects on the Lower American River. iconPresentation Slides

Public Meeting: American River Common Features (ARCF) Supplemental EIS/Subsequent EIR (Nov. 2/30, 2022)USACE is preparing to draft a Supplemental Environmental Impact Statement/Subsequent Environmental Impact Review (SEIS/SEIR) to analyze changes made during final preliminary design of multiple contract actions within the American River Common Features (ARCF) project that could result in potentially significant environmental effects. This supplemental document will centralize where the public and agencies can look for the most current project information and will bring environmental considerations up to date. The SEIS/SEIR will focus on new or different features of project designs that have evolved since the original 2016 ARCF General Reevaluation Report (GRR) Final Environmental Impact Statement/Final Environmental Impact Report (FEIS/FEIR) was completed, while analyzing the potential environmental impacts of these changes.

The Notice of Intent (NOI) to prepare the draft SEIS/SEIR can be found iconHERE. The NOI incorrectly states that the public comment period closes on November 31, 2022. A correction was made to accurately reflect the correct public comment period closing date of December 1, 2022. The correction can be found iconHERE.  The public scoping period has been extended to December 31, 2022.

Virtual public meetings were held November 2 and November 30, 2022, to discuss the development of the Draft SEIS/SEIR. Public comments will be accepted until December 31, 2022, and can be submitted to ARCF_SEIS@usace.army.miliconVirtual Scoping Meeting Presentation Slides (Updated November 30) iconVirtual Scoping Meeting Recording

USACE to discuss American River erosion protection work at June 15 virtual public meeting (June 11, 2020)

Sacramento District projects get $2.1 billion in supplemental appropriation (July 9, 2018)

Public Meeting: Lower American River Erosion Contract 3A (May 5, 2022)
This virtual public meeting discussed the Draft Supplemental Environmental Assessment/Environmental Impact Report.  Project leaders gave a presentation discussing the proposed work, environmental impacts, and answered questions related to the project. iconPublic Meeting Presentation Slides

Documents & Reports (Archive)

Status of the American River Common Features (ARCF) 2016 Flood Risk Management Project, Draft Supplemental Environmental Impact Statement/Subsequent Environmental Impact Report XIV (SEIS/SEIR)
The ARCF 2016 Flood Risk Management Project SEIS/SEIR XIV was prepared to address design refinements made to the 2016 ARCF General Reevaluation Report (GRR) Final EIS/EIR. Refinements include changes to designs associated with the Magpie Creek Project, American River Erosion Contract 3B, 4A, and 4B, Sacramento River Erosion Contract 3, American River Mitigation Site, Sacramento River Mitigation Site, and installation of a Piezometer Network.

USACE and the non-federal Partners received public comments from December 22, 2023, until February 23, 2024, during the extended comment period of 63 days. We are no longer accepting comments and have shifted focus to finalize the comprehensive comment log to ensure every comment is captured and adequately responded to by a subject matter expert, including environmental resources, engineering, project management staff. For perspective, we have logged nearly 900 comment letters. The Public Involvement appendix of the Final SEIS/SEIR will include all public and agency comments and responses, and the resulting text changes made to the SEIS/SEIR.

Announcements for future public outreach associated with the Project Components in this SEIS/SEIR will be posted on www.sacleveeupgrades.com

Any further questions regarding the ARCF 2016 Project can be directed to USACE. Public Affairs Office: SPK-PAO@usace.army.mil

The public may still view the Draft SEIS/SEIR at the links below, and the recorded public meetings held on January 10th, and 16th, 2024 under the Public Engagements tab.

The Draft SEIS/SEIR is available here: icon Draft SEIS-SEIR Report

The Draft SEIS/SEIR Appendices are available here:  iconDraft SEIS-SEIR Appendices

Note: A public commenter brought to our attention that Section 3.5.2 American River Erosion Contracts 3B North, 3B South, and 4B, in the Draft SEIS/SEIR omitted Figures 3.5.2-11 and 3.5.2-12 (page 3-42). These diagrams have been available to the public in the Presentation Slides under Public Engagements on Slide Number 11. You may also view the link below. These Figures will be added to the Final SEIS/SEIR.

iconFigure 3.5.2-11, 3.5.2-12

iconLAR C3B trees upstream 20240216

iconLAR C3B trees downstream 20240216

Answers to Frequently Asked Questions can be found hereiconFAQ

USACE published the Notice of Intent (NOI) to prepare the ARCF SEIS/SEIR in the Federal Register (Vol. 87, No. 194) on October 7, 2022, with an update posted in the Federal Register (Vol. 87, No. 199) on October 17, 2022. 

Original NOI can be found iconHERE.  

Corrected NOI which extended the scoping period can be found iconHERE.  

The public scoping period was extended to December 31, 2022.

Public scoping for this SEIS/SEIR was initiated in November 2022. Virtual public scoping meetings were held November 2, and November 30, 2022, to discuss the development of the Draft SEIS/SEIR. Scoping resulted in 69 categorized comments, one-third of which were related to habitat mitigation concerns. Appendix A, Scoping Report, in the Draft SEIS/SEIR contains scoping comments and the corresponding responses. The presentation slides and meeting recording can be found here:

iconVirtual Scoping Meeting Presentation Slides (Updated November 30)

iconVirtual Scoping Meeting Recording

American River Contract 3A Final SEA/SEIR (Nov 2022)
iconFinal SEA Report

iconFinal SEIR Report

iconFinal SEA-SEIR Appendices

iconFinal SEA Finding of No Significant Impact (FONSI)

iconFinal SEIR Notice of Determination 

American River Contract 3A Draft SEA/SEIR (April 2022/July 2022 Recirculated)
iconDraft SEA Notice of Availability (Recirculated)

iconDraft SEA (Recirculated)

iconDraft SEA Appendix (Recirculated)

iconNotice of Availability

iconDraft SEA/SEIR Report

iconFrequently Asked Questions

Frequently Asked Questions (Archive)

Collapse All Expand All
Expand List item 37887Collapse List item 37887  6. Don’t trees help prevent erosion?
 

Tree roots can provide some protection from erosion at low flows, but under higher conditions they may be a liability. For example, at high flows water may rise into the canopy of many trees within the parkway. When high velocities push against the canopy of trees the resulting forces can pull the entire tree out of the ground leaving a hole, accelerating erosion, and potentially compromising the levee. Additionally, high velocities around tree trunks may cause turbulence downstream which creates erosion. For these reasons trees are restricted from some areas near the levees.

But these are not the reasons why trees are being removed in our current work areas. The trees are being removed because in most cases rock protection cannot be properly installed around existing vegetation therefore it must be removed within the construction footprint (see question above).After construction the area will be replanted with native trees, shrubs, and grasses to gain the erosion and habitat benefits that they afford.

Expand List item 37888Collapse List item 37888  7. What is the mitigation plan to deal with wildlife along the section of the levee that is being cleared?
 

Unfortunately, wildlife is often displaced as a result of vegetation removal in advance of construction activities. However, these activities are timed to occur during the fall and early winter, typically the non-breeding season, when the level of impact/displacement to wildlife would be minimal. The wildlife that inhabited these areas are expected to move to adjacent habitats upstream and downstream of the construction footprint. This displacement is expected to be temporary until construction and habitat restoration activities have completed.

To mitigate the impacts to wildlife that occur as a result of habitat removal, two to three times the amount of habitat will be replaced and protected in perpetuity per the opinions of the resource agencies. This mitigation approach significantly increases the amount of habitat available to wildlife and is a way of helping to offset the temporal impacts to wildlife. The habitat mitigation provided onsite will typically completely replace the impacted habitat and depending on the bank protection design may increase the amount of available habitat compared to the original impact. The remaining habitat mitigation must be fulfilled at an “offsite” location in as close proximity to the impact site as feasible.

The vegetation establishes relatively quickly with intensive maintenance in the first 3-5 years, and it will not be long before wildlife can reclaim the area. The bank protection sites implemented during the late 90’s and early 2000’s have demonstrated that successful habitat is achievable.

Expand List item 37889Collapse List item 37889  8. How do riverbank erosion control measures protect levees that are sometimes set back far away from the actual riverbank, like in Campus Commons?
 

Advanced computer modeling is used to determine how the river will behave and where erosion is likely to occur under high water conditions. These models are studied to determine the best location to place protective features and control erosion which could threaten the levees. Sometimes the best place to put protective rock features is not on the levee but along the riverbank near the water’s edge.

Expand List item 37890Collapse List item 37890  9. How is the American River Bike Trail or any other walking and equestrian trails in the American River Parkway impacted?
 

Haul trucks and other construction equipment need to use or cross portions of recreational trails located within the American River Parkway to move materials to the construction and mitigation sites. In areas where construction equipment is required to only cross an existing trail, flaggers would be present to direct traffic. Where larger portions of a trail are impacted or required for construction access, the trail would be temporarily rerouted away from the construction area. Any required detours would be developed in consultation with the City of Sacramento and Sacramento County Regional Parks.  Signage would be posted at the affected locations a minimum of 14-days in advance.

Expand List item 37891Collapse List item 37891  10. What are the types of trees that will be planted on-site?
 

The on-site mitigation goal is to ensure that plantings associated with the revegetation of the levee provide a robust habitat for native species and are fully compatible with the surrounding environment. The erosion protection improvements will include the construction of a planting bench along the waterside toe of the levee to support on-site mitigation that includes trees and shrubs. The tree mix will include Boxelder, White Alder, Oregon Ash, Sycamore, Cottonwood, Oaks, and Willows. Complementing the tree plantings will be a variety of native shrub species that include mugwort, button bush, wild rose, sandbar willow and wild grape, as well as groundcovers that extend further up the slope of the waterside levee.

Expand List item 37892Collapse List item 37892  11. What will happen to the on-site mitigation during elevated river flows prior to it being fully established?
 

On-site mitigation typically can survive elevated flows however if elevated flows cause damage and plantings need to be replaced during the establishment period, the project partners will replace them. (Continue reading FAQs for more information regarding on-site mitigation, and visit the ARCF 2016 Mitigation web page.)

Expand List item 37893Collapse List item 37893  12. How are elderberry plants located in the project footprint being addressed? Where are the USACE-specific offsite mitigation areas and what type of plantings will occur there?
 

Elderberry plants, which provide habitat for the protected Valley Elderberry Longhorn Beetle, are being relocated and transplanted to off-site mitigation sites. In addition, the project is planting approximately 55 acres of new Elderberry habitat within the parkway.

The offsite mitigation sites include Rio Americano East and West, Rossmoor East and West, Glenn Hall/Paradise Beach, and the American River Mitigation Site as shown on the map below. Additional mitigation information can be found at the ARCF 2016 Mitigation web page.

The mitigation site plantings will include a broad variety of native trees and bushes which vary by site. The tree species will include a mixture of Sycamore, Cottonwood, Valley Oak, Interior Live Oak. Bush and plant species will include, among others, Coyote Brush, Western Redbud, Rose, Coffeeberry, Elderberry, Clematis, Western Goldenrod, Evening Primrose, Mugwort, Rose, Yarrow, Deergrass, and Creeping Wildrye.

Expand List item 37894Collapse List item 37894  13. What is the purpose of tying down trees and woody material at the riverbank?
 

The erosion protection sites include instream woody material that is tied down at the riverbank. It is intended to stay in place and provide habitat for juvenile fish migrating downstream. As the planted vegetation grows the instream woody materials will degrade through natural processes and their function will be provided by the new mature, live vegetation.

Expand List item 37895Collapse List item 37895  14. What should I expect during construction?
 

Typically, site preparation begins between October – May with trimming and/or removal of vegetation located with the construction footprint. Bank protection construction usually occurs between May and November, outside of flood season. On-site planting typically follows in the spring and summer following the completion of the riverbank construction. In general, work hours are Monday through Saturday from 7:00 a.m. to 6:00 p.m. for locations within the city of Sacramento and Monday through Friday from 6:00 a.m. to 8:00 p.m. and Saturday from 7:00 a.m. to 8:00 p.m. in the unincorporated areas of the county.

Neighborhoods located near project areas will be notified of specific work hours, haul routes, ingress and egress points, staging areas, detours, lane closures (if any), and affected recreational facilities(including bike paths) prior to the commencement of construction activities.

Expand List item 37896Collapse List item 37896  15. Site 2-1 at Glenn Hall Park is now open to the public. Why do trucks keep going in and out?
 

The construction roadway through Glenn Hall Park will remain until completion of the work near I-80 bridge. The construction roadway through the park is now being used by Caltrans and their contractor, Granite construction. When C3A beings work in the spring of 2024, GHP will be used to egress from the work site at I-80 bridge.

Expand List item 37897Collapse List item 37897  16. Are the fabric, fiber rolls and stakes in place at recently completed project sites biodegradable and what will happen to them over time?
 

In order to revegetate the sites and restore their natural beauty, topsoil must be protected from runoff erosion until grasses and other vegetation can take root. This is done with erosion control fabric and fiber rolls which are held in place by stakes. The protective devices were designed for the current rain and high water conditions, and they are doing a good job protecting the site. The fabric, fiber rolls and stakes are all biodegradable and will last long enough for vegetation to establish before deteriorating. (The green stakes may appear to be plastic, but they are biodegradable and will degrade into water, C02 and compost.).

The recently completed projects sites will be fully revegetated in subsequent “greening” contracts. Revegetation of the levee slope and riverbank typically occurs in the springtime, following completion of the erosion protection construction. The on-site mitigation and plant establishment is monitored and maintained as needed by the project sponsors for 3 to 5 years.

Expand List item 37898Collapse List item 37898  17. How else can I get more information on the project?
 

Subscribe for updates! On this page, in the left-hand column, look for the “Subscribe for Construction and Traffic email updates” button, or, copy and paste the following into an email: spk-pao@usace.army.mil and place "add me to your ARCF mailing list" in the subject line.

You can also follow our social media channels on Facebook and Twitter.

Expand List item 37899Collapse List item 37899  18. Who is the point of contact during this project?
 

Residents with questions or concerns about the project should contact the USACE Public Affairs Office by telephone at (916) 557-5100 or email spk-pao@usace.army.mil

We're managing multiple projects within the region, and we'll do our best to respond as quickly as possible. Any serious emergency or life-threatening situation that is witnessed, such as theft in progress or vandalism, should be reported to local law enforcement immediately.