  • USACE awards $29.5 million construction contract for Sacramento River levee improvements

    The U.S. Army Corps of Engineers Sacramento District awarded a $29.5 million construction contract on January 15 to Nordic Industries Inc. of Olivehurst, for 1.8 miles of levee improvements at four sites along the Sacramento River East Levee. Construction in 2021 will entail installation of seepage cutoff walls on both sides of Business 80/Highway 50 just upstream of Miller Park, on the south side of the little pocket, and on the north side of the big pocket.
  • Nighttime lane closures for H Street Bridge set for May 19-20

    Traffic on Sacramento's H Street Bridge will be reduced to one lane in each direction May 19 and 20, from around 9 p.m. until 5 a.m. The U.S. Army Corps of Engineers Sacramento District is finalizing levee work at the bridge's western end, where crews will be conducting minor excavation and concrete work during the lighter traffic hours.